Buses

Garage Rebuilds and Bus Electrification

MBTA is currently preparing for the launch of battery-electric buses (BEBs) as part of the Bus Electrification Project. Correspondingly, it is planning rebuilds and renovations of all bus garages to include charging equipments.

New Arborway Bus Maintenance Facility

Status: 15% design? (as of October 2023)

Details TBA

Commuter Rail

Future Planning of Facilities

Layover Facility Alternatives Analysis (2013)

Status: Alternatives Analysis (AA) complete

In March 2013, MassDOT did an Alternative Analysis (AA) on commuter rail layover facilities, as part of the South Station Expansion project.

More details of the study TBC. (ArchBoston user F-Line to Dudley briefly explained here that Widett Circle was the most preferred, followed by Beacon Park Yard (West Station) and Readville Yard as backup options.)